Problem:
The location of this municipal waste water treatment plant does not have adequate clay for water containment.
Solution:
Moore & Bruggink Architects and Engineers chose 30 mil PVC to line the three waste water containment ponds in Howard City, MI.

Above: Site preparation and final grading
Kamminga and Roodevoets, Inc. built the ponds and contracted with EPI to fabricate and install the 30 mil PVC geomembrane liner.

Above: Installation of the PVC geomembrane liner
Sealing of the PVC was accomplished using chemical fusion welding.

Above: Completed Waste Water Treatment Pond
Years of leak free, trouble free performance from PVC geomembrane liner.