Solutions


Problem:

The location of this municipal waste water treatment plant does not have adequate clay for water containment.

Solution:

Moore & Bruggink Architects and Engineers chose 30 mil PVC to line the three waste water containment ponds in Howard City, MI.

Pond excavation

Above: Site preparation and final grading

Kamminga and Roodevoets, Inc. built the ponds and contracted with EPI to fabricate and install the 30 mil PVC geomembrane liner.

30 mil PVC Geomembrane

Above: Installation of the PVC geomembrane liner

Sealing of the PVC was accomplished using chemical fusion welding.

Oxidation Pond

Above: Completed Waste Water Treatment Pond

Years of leak free, trouble free performance from PVC geomembrane liner.

For more information, contact EPI at 1-800-OK-LINER.